Ethiopia begins filling Nile dam in a move likely to anger Egypt, Sudan


Ethiopia has started filling the Grand Renaissance dam, a giant hydroelectric project it is building on the Blue Nile, its water minister said on Wednesday, a day after talks with Sudan and Egypt on the issue became deadlocked.

“The construction of the dam and the filling of the water go hand in hand,” Seleshi Bekele said in televised comments. “The filling of the dam doesn’t need to wait until the completion of the dam.”

The water level had increased from 525 metres to 560 metres, he said.

Egyptian and Sudanese officials could not immediately be reached for comment, but the move is likely to spark fierce protests from those countries, which also depend on the Nile’s waters and have sought a legally binding agreement before it could be filled.

Tortuous, often acrimonious negotiations spanning close to a decade have left the three nations short of an agreement to regulate how Ethiopia will operate the dam and fill its reservoir, including talks on Tuesday.

The $4 billion US Grand Ethiopian Renaissance Dam will have an installed capacity of 6,450 megawatts — more than doubling its existing capacity — and is the centrepiece of Ethiopia’s bid to become Africa’s biggest power exporter.

But it has raised concerns in Cairo that already limited Nile waters, on which its population of more than 100 million is almost entirely dependent, would be further restricted. Egypt gets 90 per cent of its fresh water from the Nile.

Needed for economic growth: Ethiopia

The Nile Basin river system flows through 11 countries. The Blue Nile and White Nile, its tributaries, merge in Sudan before flowing into Egypt and toward the Mediterranean. The dam is being built about 15 kilometres from the border with Sudan on the Blue Nile, source of most of the Nile’s waters.

A handout satellite image shows a view of the Grand Ethiopian Renaissance Dam (GERD) and the Blue Nile River in Ethiopia on July 12. (Maxar Technologies/Reuters)

Egypt has accused Ethiopia of not factoring in the risk of drought conditions such as those that affected the Nile Basin in the late 1970s and early 1980s.

Addis Ababa has countered by arguing Cairo is trying to hold the project hostage by imposing rules over the filling and operation of the dam.

Ethiopia had earlier said it would begin to use seasonal rains to fill the dam around this time. It has said the project is essential to its economic development, telling the United Nations Security Council in a letter last month it is designed “to help extricate our people from abject poverty.”

It has also said that while it could fill the reservoir in two to three years, it made a concession by proposing a four-to-seven-year process.

Read more at CBC.ca